Governor Greg Abbott ordered a halt to approving new data center connections to the Texas grid until regulators audit each project's power and water use, tax breaks, community impact and ownership. The queue is enormous: grid operator ERCOT is tracking more than 1,800 projects asking for over 474 gigawatts — more than five times the grid's record peak demand — and about 90% of those requests are data centers. Projects that fail the audit will be denied a connection; no timeline has been set.